Pattikad-Vettilapara Road
Completed100%Physical progress
87.5%Financial progress
Scheduled start13-01-2023
Scheduled completion18-11-2025
- Contractor
- ASSMASConstructions Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹20,89,53,040₹20.9 crore
- Amount paid
- ₹18,58,08,942₹18.58 crore
- Paid to contractor
- ₹17,39,99,024₹17.4 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹21,37,20,000₹21.37 crore
- Technical sanction (TS)
- ₹21,05,00,000₹21.05 crore
- Tender amount
- ₹21,27,35,155₹21.27 crore
- Letter of acceptance (LOA)
- ₹18,02,84,029₹18.03 crore
- Current progress
- Tendering stage