Total of works

₹83.17 crore

₹83,16,89,762

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Vallithod to Ambayathod

Scheduled completion was 13-10-2025. That was 354 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Vallithod to Ambayathod

In progress
76.3%Physical progress
59.8%Financial progress
Scheduled start15-10-2022
Scheduled completion13-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹79,91,01,849₹79.91 crore
Amount paid
₹47,76,91,348₹47.77 crore
Paid to contractor
₹44,73,29,590₹44.73 crore
Financial sanction (FS)
₹83,16,89,762₹83.17 crore
Technical sanction (TS)
₹81,43,95,333₹81.44 crore
Tender amount
₹58,27,62,196₹58.28 crore
Current progress
Tendered. Placed in tender approval committee on 29.04.2022. PED approval pending at KIIFB

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹83,16,89,762₹83.17 crore

Details

Project code
PWD013-26-01
Department
Public Works
Constituency
Irikkur,Peravoor

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026