Total of works

₹82.49 crore

₹82,49,23,102

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · #1

Scheduled completion was 31-12-2025. That was 275 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Work 1

In progress
32%Physical progress
18.9%Financial progress
Scheduled start21-03-2024
Scheduled completion31-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹27,24,93,888₹27.25 crore
Amount paid
₹5,16,17,542₹5.16 crore
Paid to contractor
₹4,83,36,735₹4.83 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹82,49,23,102₹82.49 crore
Technical sanction (TS)
₹28,23,77,087₹28.24 crore
Tender amount
₹27,24,93,888₹27.25 crore

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹82,49,23,102₹82.49 crore

Details

Project code
PWD013-34-01
Department
Public Works
Constituency
Perambra

What we don't know yet