Total of works

₹50.58 crore

₹50,57,80,606

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Kanjirampara - Kalikavu

Approved
0%Physical progress
Not publishedFinancial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹50,57,80,606₹50.58 crore
Technical sanction (TS)
₹48,19,10,000₹48.19 crore
Tender amount
₹42,79,40,270₹42.79 crore

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹50,57,80,606₹50.58 crore

Details

Project code
PWD013-47-01
Department
Public Works
Constituency
Wandoor

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kanjirampara - Kalikavu
  • Scheduled start and completion dates · Kanjirampara - Kalikavu
  • Amount paid · Kanjirampara - Kalikavu

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…