Kanakkuമലയാളം

Total of works

₹86.25 crore

₹86,24,91,912

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Work 1

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹65,00,00,00,000₹6,500 crore
Financial sanction (FS)
₹86,24,91,912₹86.25 crore
Current progress
Site visit was done in May and some minor chjanges in alignment was suggested and SPV is in the process of modifying the same. Proceedings will be issued once the process is completed.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹86,24,91,912₹86.25 crore

Details

Project code
PWD014-47
Department
Public Works
Constituency
Beypore

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · #1
  • Scheduled start and completion dates · #1
  • Amount paid · #1

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…