Vithura-Bonacaud Road
In progress98%Physical progress
78.9%Financial progress
Scheduled start25-11-2019
Scheduled completion30-11-2023
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹29,77,67,835₹29.78 crore
- Amount paid
- ₹23,49,76,402₹23.5 crore
- Paid to contractor
- ₹21,94,47,605₹21.94 crore
- Administrative sanction (AS)
- ₹35,00,00,000₹35 crore
- Financial sanction (FS)
- ₹30,65,52,853₹30.66 crore
- Technical sanction (TS)
- ₹30,97,70,200₹30.98 crore
- Tender amount
- ₹29,77,67,835₹29.78 crore
- Letter of acceptance (LOA)
- ₹29,77,67,835₹29.78 crore
- Current progress
- Work progress 73% . Drain - 5600/7000 m done, Side protection work - 2000m done GSB - completed. WMM - 5/7 km completed. DBM - 5/7 km completed. TOC extension requested upto 31.08.2022 Purambokke assessed and to be evicted. Puramboke sketches submitte