Muvattupuzha town portion
In progress76%Physical progress
57.3%Financial progress
Scheduled start09-01-2023
Scheduled completion30-10-2025
- Contractor
- Pksulpheekerinfrastructurellp
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹22,34,69,497₹22.35 crore
- Amount paid
- ₹12,81,31,700₹12.81 crore
- Paid to contractor
- ₹11,99,87,696₹12 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹45,59,65,394₹45.6 crore
- Technical sanction (TS)
- ₹22,34,69,497₹22.35 crore
- Tender amount
- ₹26,54,86,871₹26.55 crore
- Letter of acceptance (LOA)
- ₹22,49,88,874₹22.5 crore
- Current progress
- FS obtained for Rs.32.14 Cr. LA procedure for acquiring balance land of 12.086 Are is in progress.KWA estimate is approved by KIIFB on 07-02-2022. Based on the suggestions issued by KIIFB, revised estimate by KSEB has submitted. The work is tendered