Muringoor- Ezhattumugham road
In progress45%Physical progress
34.4%Financial progress
Scheduled start14-10-2024
Scheduled completion13-04-2026
- Contractor
- M/s BAABConstruction Pvt. Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹27,45,25,389₹27.45 crore
- Amount paid
- ₹9,45,31,825₹9.45 crore
- Paid to contractor
- ₹8,85,23,431₹8.85 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹39,05,24,747₹39.05 crore
- Technical sanction (TS)
- ₹21,90,70,000₹21.91 crore
- Tender amount
- ₹27,45,25,389₹27.45 crore
- Current progress
- CD works : Culvert Reconstruction 14 out of 17 completed, 3 Nos not started ;Culvert Widening completed 1 out of 14, 10 in progress, 3Nos not yet started DBM: Proposal 12.2km- 4.35 km completed(Ch 3/290 Kallukuthy Jn to Ch7/665 Kunnappilly Nirmala colle