Kanakkuമലയാളം
PWD015-06-04 Chalakudy

Improvements to Muringoor - Ezhattumugham Road from KM 0/000 – 17/205, Thrissur District- Balance work -Contract

Spent on this package so far

₹15.04 crore

₹15,04,33,617

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Muringoor- Ezhattumugham road

Scheduled completion was 13-04-2026. That was 172 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Muringoor- Ezhattumugham road

In progress
45%Physical progress
34.4%Financial progress
Scheduled start14-10-2024
Scheduled completion13-04-2026
Implementing agency (SPV)
KRFB
Contract amount
₹27,45,25,389₹27.45 crore
Amount paid
₹9,45,31,825₹9.45 crore
Paid to contractor
₹8,85,23,431₹8.85 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹39,05,24,747₹39.05 crore
Technical sanction (TS)
₹21,90,70,000₹21.91 crore
Tender amount
₹27,45,25,389₹27.45 crore
Current progress
CD works : Culvert Reconstruction 14 out of 17 completed, 3 Nos not started ;Culvert Widening completed 1 out of 14, 10 in progress, 3Nos not yet started DBM: Proposal 12.2km- 4.35 km completed(Ch 3/290 Kallukuthy Jn to Ch7/665 Kunnappilly Nirmala colle

Money trail

Estimated amount
₹39,05,24,747Estimate of sub-project PWD015-06, shared by 2 contract packages
Expenditure reported · this package
₹15,04,33,617
Expenditure reported · all 2 packages
₹23,56,73,96960.3% of the estimated amount

Details

Project code
PWD015-06-04
Department
Public Works
Constituency
Chalakudy
Name as KIIFB publishes it
IMPROVEMENTS TO MURINGOOR - EZHATTUMUGHAM ROAD FROM KM 0/000 – 17/205, THRISSUR DISTRICT- Balance work -Contract

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements to Muringoor - Ezhattumugham Road from KM 0/000 ? 17/205, Thrissur District”. The figures below are for that whole project, not this package alone.

Approved
₹39,05,24,747₹39.05 crore
Paid so far
₹35,43,02,03890.7% of the amount approved

This package

Work awarded
₹23.84 crorepaid
₹27.45 croreapproved

Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project