Killy EMS Academy Road
In progress52.7%Physical progress
37.2%Financial progress
Scheduled start25-06-2024
Scheduled completion24-12-2025
- Contractor
- Vishwa Samudra Engineering Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹22,52,90,756₹22.53 crore
- Amount paid
- ₹8,37,86,648₹8.38 crore
- Paid to contractor
- ₹7,19,78,990₹7.2 crore
- Financial sanction (FS)
- ₹24,45,82,595₹24.46 crore
- Technical sanction (TS)
- ₹22,52,90,757₹22.53 crore
- Tender amount
- ₹22,52,90,756₹22.53 crore
- Current progress
- FDR work tender approval in processing. KWA utility shifting estimate submitted to KIIFB. Puramboke land assessment in progress by Revenue Dept