Thiruvananthapuram Neyyar Dam Road
In progress6.6%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹58,93,21,449₹58.93 crore
- Current progress
- Road work can be done only after completion of KWA project . LA is required for RoW of 14.50m. Survey sketches collected from Taluk Survey office concerned and approximate area calculated for acquisition. Requisition given to District Collector. BC overl