Pazhakutty Mangalapuram road
Approved0%Physical progress
86.7%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹40,98,00,000₹40.98 crore
- Amount paid
- ₹35,53,00,000₹35.53 crore
- Paid to contractor
- ₹33,22,00,000₹33.22 crore
- Administrative sanction (AS)
- ₹2,00,00,00,000₹200 crore
- Financial sanction (FS)
- ₹1,69,95,69,425₹169.96 crore
- Technical sanction (TS)
- ₹42,54,00,000₹42.54 crore
- Tender amount
- ₹40,98,00,000₹40.98 crore
- Letter of acceptance (LOA)
- ₹36,59,00,000₹36.59 crore
- Current progress
- RReach I work 34% progress. Drain - 6200/13520 m placed, 10050/13520 m casted Retaining wall - 88% done, Culvert - 14/15 completed, 1 ongoing GSB - 4.1 km, WMM - 4.05km, DBM-1.64 km + 0.908 km(Vembayam side) Bridge - pile completed (8 Nos.), pile cap 2