Total of works

₹169.96 crore

₹1,69,95,69,425

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Pazhakutty Mangalapuram road

Reported financial progress is 86.7% and reported physical progress is 0%, a gap of 86.7 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Pazhakutty Mangalapuram road

Approved
0%Physical progress
86.7%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
₹40,98,00,000₹40.98 crore
Amount paid
₹35,53,00,000₹35.53 crore
Paid to contractor
₹33,22,00,000₹33.22 crore
Administrative sanction (AS)
₹2,00,00,00,000₹200 crore
Financial sanction (FS)
₹1,69,95,69,425₹169.96 crore
Technical sanction (TS)
₹42,54,00,000₹42.54 crore
Tender amount
₹40,98,00,000₹40.98 crore
Letter of acceptance (LOA)
₹36,59,00,000₹36.59 crore
Current progress
RReach I work 34% progress. Drain - 6200/13520 m placed, 10050/13520 m casted Retaining wall - 88% done, Culvert - 14/15 completed, 1 ongoing GSB - 4.1 km, WMM - 4.05km, DBM-1.64 km + 0.908 km(Vembayam side) Bridge - pile completed (8 Nos.), pile cap 2

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,69,95,69,425₹169.96 crore

Details

Project code
PWD015-15
Department
Public Works
Constituency
Nedumangad

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Pazhakutty Mangalapuram road
  • Scheduled start and completion dates · Pazhakutty Mangalapuram road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026