Payyannur Ambalathararoad
Completed100%Physical progress
93.6%Financial progress
Scheduled start29-01-2022
Scheduled completion10-03-2024
- Contractor
- Irikkur Construction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹47,00,91,177₹47.01 crore
- Amount paid
- ₹43,99,43,136₹43.99 crore
- Paid to contractor
- ₹41,19,80,618₹41.2 crore
- Financial sanction (FS)
- ₹58,52,98,409₹58.53 crore
- Technical sanction (TS)
- ₹47,00,91,177₹47.01 crore
- Tender amount
- ₹44,83,00,178₹44.83 crore
- Current progress
- 17% work completed. Work in progress Clearing and grubbing,Culvert,Drainage,CC retaining wall,DR works in progress. Concrete works of culverts are in progress.Piling work of bridge started.4 nos.completed.