Pallimukku- Alimukku Road
In progress78.1%Physical progress
43.8%Financial progress
Scheduled start05-04-2022
Scheduled completion30-10-2025
- Contractor
- Lsripl-as(jv)
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹37,76,47,804₹37.76 crore
- Amount paid
- ₹16,52,44,363₹16.52 crore
- Paid to contractor
- ₹15,25,73,878₹15.26 crore
- Administrative sanction (AS)
- ₹12,00,00,000₹12 crore
- Financial sanction (FS)
- ₹46,38,31,589₹46.38 crore
- Technical sanction (TS)
- ₹45,33,36,282₹45.33 crore
- Tender amount
- ₹37,76,47,804₹37.76 crore
- Current progress
- TS Estimate for upgradation work under FDR Technology submitted to PD. Work tendered. Financial bid opened and will be placed before next tender approval committe. Sanction has been accorded for Patch repair work for Rs 44 L. No body responded for the