Kottavattom mukku Kottavattom school Road
Under appraisal0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹11,00,00,000₹11 crore
- Current progress
- DPR as per TAR was prepared by PPU and submiitted to KIIFB. Reply to the TAR was submitted. Reply to the observation on TAR reply is under preparation