Kondotty-Edavannappara - Areacode road
Completed100%Physical progress
94%Financial progress
Scheduled start01-01-2022
Scheduled completion05-08-2024
- Contractor
- Malabar Tech
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹71,91,28,197₹71.91 crore
- Amount paid
- ₹67,56,33,827₹67.56 crore
- Paid to contractor
- ₹63,22,62,687₹63.23 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹1,03,06,83,620₹103.07 crore
- Technical sanction (TS)
- ₹71,91,28,197₹71.91 crore
- Tender amount
- ₹68,94,22,273₹68.94 crore
- Current progress
- work is ongoing . land is surrendered from land owners by free of cost. but in 5 town potions (muthuvallur, mundakkulam ,ponnad,edavannappara,vavoor) have LA proposal . FS obtained from revenue department .The KIIFB LA Special Tahsildar requested for sub