Kuthuparamba Ring Road
In progress52.9%Physical progress
33.5%Financial progress
Scheduled start08-11-2021
Scheduled completion28-02-2026
- Contractor
- K. Muhammed Haji
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹15,48,08,412₹15.48 crore
- Amount paid
- ₹5,18,61,532₹5.19 crore
- Paid to contractor
- ₹4,90,04,746₹4.9 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹40,23,79,235₹40.24 crore
- Technical sanction (TS)
- ₹32,08,00,000₹32.08 crore
- Tender amount
- ₹15,48,08,412₹15.48 crore
- Letter of acceptance (LOA)
- ₹13,82,21,796₹13.82 crore
- Current progress
- 6 (1) notification published on 03/11/2021. Planting of Boundary stone completed in Kuthuparamba-Pazhayanirath road (1.786km) . Planting of Boundary stone in Kuttikkunnu-Pazhayanirath road (3.985km) in progress. Rectification work completed.Joint inspect