Madayi-Ettikkulam HS-Palakkode Road
Completed100%Physical progress
95%Financial progress
Scheduled start12-07-2021
Scheduled completion25-10-2025
- Contractor
- T. AAbdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,97,13,791₹13.97 crore
- Amount paid
- ₹13,26,75,409₹13.27 crore
- Paid to contractor
- ₹12,52,22,318₹12.52 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹20,84,34,885₹20.84 crore
- Technical sanction (TS)
- ₹13,97,13,792₹13.97 crore
- Tender amount
- ₹13,59,23,556₹13.59 crore
- Letter of acceptance (LOA)
- ₹13,59,23,556₹13.59 crore
- Current progress
- Additional piles for box culverts are in progress. KSEB utility shifting work is to be done. Pile caps concrete works completed. Pier concreting works completed.Pier head concreting works completed.Bridge shuttering work between P3 and P4 in progress.