Kanakkuമലയാളം

Madayi-Ettikkulam HS-Palakkode Road and Construction of Vengara Over Bridge -Phase I- Construction of Vengara ROB-Contract work

Spent on this package so far

₹12.81 crore

₹12,80,88,880

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Madayi-Ettikkulam HS-Palakkode Road

Completed
100%Physical progress
95%Financial progress
Scheduled start12-07-2021
Scheduled completion25-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹13,97,13,791₹13.97 crore
Amount paid
₹13,26,75,409₹13.27 crore
Paid to contractor
₹12,52,22,318₹12.52 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹20,84,34,885₹20.84 crore
Technical sanction (TS)
₹13,97,13,792₹13.97 crore
Tender amount
₹13,59,23,556₹13.59 crore
Letter of acceptance (LOA)
₹13,59,23,556₹13.59 crore
Current progress
Additional piles for box culverts are in progress. KSEB utility shifting work is to be done. Pile caps concrete works completed. Pier concreting works completed.Pier head concreting works completed.Bridge shuttering work between P3 and P4 in progress.

Money trail

Estimated amount
₹28,68,39,795Estimate of sub-project PWD015-45, shared by 2 contract packages
Expenditure reported · this package
₹12,80,88,880
Expenditure reported · all 2 packages
₹12,80,88,88044.7% of the estimated amount

Details

Project code
PWD015-46-02
Department
Public Works
Constituency
Payyannur,Kalliasseri
Name as KIIFB publishes it
MADAYI-ETTIKKULAM HS-PALAKKODE ROAD AND CONSTRUCTION OF VENGARA OVER BRIDGE -PHASE I- CONSTRUCTION OF VENGARA ROB-Contract work

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project