REC Koodathai Road
In progress55%Physical progress
34.4%Financial progress
Scheduled start04-03-2024
Scheduled completion03-03-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹58,39,81,821₹58.4 crore
- Amount paid
- ₹20,10,29,027₹20.1 crore
- Paid to contractor
- ₹18,82,51,712₹18.83 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹60,99,87,800₹61 crore
- Technical sanction (TS)
- ₹58,39,93,699₹58.4 crore
- Tender amount
- ₹58,39,81,821₹58.4 crore
- Current progress
- FS obtained. Free surrunder form from each land owner has to obtained for TS submission. Meeting was conducted by Hon. MLA's of Kunnamangalam & Koduvally for obtaining willingness document from affected people. Local road committees are working for obtai