Manassery-Pulparamba-Chullikkaparamba
Approved0%Physical progress
62.4%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹25,11,00,000₹25.11 crore
- Amount paid
- ₹15,67,00,000₹15.67 crore
- Paid to contractor
- ₹14,66,00,000₹14.66 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹36,79,53,794₹36.8 crore
- Technical sanction (TS)
- ₹28,36,00,000₹28.36 crore
- Tender amount
- ₹25,11,00,000₹25.11 crore
- Current progress
- Culvert work , retaining wall , drainage ,Sub grade formation and GSB laying progressing at various locations. Tree cutting also progressing