Pasuvannara-Keezharoor Ring road
In progress30%Physical progress
30.5%Financial progress
Scheduled start25-06-2024
Scheduled completion24-06-2025
- Contractor
- Vishwa Samudra Engineering Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,77,09,332₹13.77 crore
- Amount paid
- ₹4,20,14,853₹4.2 crore
- Paid to contractor
- ₹3,59,32,670₹3.59 crore
- Financial sanction (FS)
- ₹19,75,82,239₹19.76 crore
- Technical sanction (TS)
- ₹11,52,38,943₹11.52 crore
- Tender amount
- ₹13,77,09,332₹13.77 crore
- Current progress
- FDR work tender approval in processing. LA to proceed with the revised alignment prepared by KIIFB.