PWD015-78-01 Mattannur

Karetta-Maloor road (Karetta-Kanchilery-Kunderipoyil-Maloor) Km 0/000 to 9/600 - Contract file

Estimated amount

₹28.3 crore

₹28,29,71,378 · ₹23.77 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Karetta-Maloor road

Completed
100%Physical progress
87.2%Financial progress
Scheduled start15-03-2022
Scheduled completion11-11-2025
Implementing agency (SPV)
KRFB
Contract amount
₹27,60,72,058₹27.61 crore
Amount paid
₹24,06,20,625₹24.06 crore
Paid to contractor
₹22,52,91,029₹22.53 crore
Financial sanction (FS)
₹26,08,78,910₹26.09 crore
Technical sanction (TS)
₹27,60,72,058₹27.61 crore
Tender amount
₹22,73,61,366₹22.74 crore
Current progress
Site handed over on 15/03/2022.Work started.Culvert and side protection works are progressing.

Money trail

Estimated amount
₹28,29,71,378₹28.3 crore
Expenditure reported
₹23,77,31,91984% of the estimated amount

Details

Project code
PWD015-78-01
Department
Public Works
Constituency
MattannurMLA: Smt. K.K. Shailaja Teacher

What KIIFB approved and paid

On KIIFB's project status page this belongs to “2017-18 Improvements to Karetta-Maloor road (Karetta-Kanchilery-Kunderipoyil-Maloor) Km 0/000 to 9/600 in Kannur district”.

Approved
₹28,29,71,378₹28.3 crore
Paid so far
₹27,73,03,72998% of the amount approved

This package

Work awarded
₹27.04 crorepaid
₹27.47 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org