Thiruvambadi-Pulloorampara road
In progress32%Physical progress
13.5%Financial progress
Scheduled start25-02-2024
Scheduled completion24-02-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,04,48,77,594₹104.49 crore
- Amount paid
- ₹14,12,50,018₹14.13 crore
- Paid to contractor
- ₹13,22,72,221₹13.23 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹1,08,16,28,590₹108.16 crore
- Technical sanction (TS)
- ₹1,05,64,99,181₹105.65 crore
- Tender amount
- ₹1,04,48,77,594₹104.49 crore
- Current progress
- Correction of TS estimate as per T S committee remarks done. The Direction to revise the proposal between Pulloorampara to Maripuzha as hill highway standard and subsequent discussion delayed the TS submission. (Due to Tunnel approach road). Hon. Thiruva