Karuvannur Katttoor road
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹43,67,71,898₹43.68 crore
- Current progress
- Encroachment survey - 2 km encroachment survey completed by revenue department under roads division, Thrissur.. FDR- Work is shortlisted in FDR category. Request letter submitted to Dist. survey suprent,Thrissur for submitting estimate for the survey wo