Sreekandapuram- Naduvil road
In progress72.3%Physical progress
56.9%Financial progress
Scheduled start13-03-2024
Scheduled completion12-03-2026
- Contractor
- M/s Irikkur Constructioncompany
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹39,92,51,805₹39.93 crore
- Amount paid
- ₹22,71,27,385₹22.71 crore
- Paid to contractor
- ₹21,26,91,307₹21.27 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹47,72,31,024₹47.72 crore
- Technical sanction (TS)
- ₹47,71,19,000₹47.71 crore
- Tender amount
- ₹39,92,51,805₹39.93 crore
- Current progress
- Design Review by KIIFB is in Progress- Additional surveys as suggested during design review has completed- Estimate to be resubmitted for TS after the completion of design review process.Alignment is under preparation by CMD. Revised topographical drawi