ETC Poomangalam- Madekkad road
In progress10.2%Physical progress
4.7%Financial progress
Scheduled start03-09-2024
Scheduled completion02-03-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹67,22,20,940₹67.22 crore
- Amount paid
- ₹3,14,97,171₹3.15 crore
- Paid to contractor
- ₹2,94,95,220₹2.95 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹69,52,90,000₹69.53 crore
- Technical sanction (TS)
- ₹65,96,86,898₹65.97 crore
- Tender amount
- ₹67,22,20,940₹67.22 crore
- Current progress
- Additional investigation completed and revised DPR costing 63.34 Cr submitted to KIIFB for approval.