Ammanappara-Chapparappadavu road
In progress94.2%Physical progress
90.1%Financial progress
Scheduled start26-12-2022
Scheduled completion15-12-2025
- Contractor
- T. AAbdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹57,42,17,053₹57.42 crore
- Amount paid
- ₹51,73,09,380₹51.73 crore
- Paid to contractor
- ₹48,88,13,487₹48.88 crore
- Financial sanction (FS)
- ₹60,76,36,268₹60.76 crore
- Technical sanction (TS)
- ₹54,90,04,858₹54.9 crore
- Tender amount
- ₹57,42,17,053₹57.42 crore
- Current progress
- TS accorded on 20/12/21.Work retendered on 16/03/2022.Financial evaluation finalised.Tender approval committee held on 22-06-2022 .Documents submitted to KIIFB for sub-project revision(Ulitity charges,excess in FS amount due to rate revision).