Peruvamparamba Kalluvayal-Nellicampoil road
In progress60.7%Physical progress
50.1%Financial progress
Scheduled start13-09-2024
Scheduled completion12-03-2026
- Contractor
- M/s Irikkur Constructioncompany
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,52,28,147₹28.52 crore
- Amount paid
- ₹13,02,07,685₹13.02 crore
- Paid to contractor
- ₹12,19,31,752₹12.19 crore
- Financial sanction (FS)
- ₹30,97,19,000₹30.97 crore
- Technical sanction (TS)
- ₹28,52,28,147₹28.52 crore
- Tender amount
- ₹25,99,07,234₹25.99 crore
- Current progress
- Exe.Director,KIIFB had given direction to revise DPR with 5.5 m carriageway and 10 meter RoW with paved shoulders as per KIIFB specification.Revised DPR and topographical details submitted to KRFB on 01-07-2022.