Kuttoth-Attakkundukadavu road
Completed100%Physical progress
91.4%Financial progress
Scheduled start02-04-2022
Scheduled completion01-08-2023
- Contractor
- Jabeer U
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹2,59,57,808₹2.6 crore
- Amount paid
- ₹2,37,37,476₹2.37 crore
- Paid to contractor
- ₹2,24,29,898₹2.24 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹12,69,90,000₹12.7 crore
- Technical sanction (TS)
- ₹2,69,90,000₹2.7 crore
- Tender amount
- ₹2,59,57,808₹2.6 crore
- Current progress
- FS accorded for LA for 10crore. LA to be done. Boundary stone planting work stopped due to protest from land owners. Though the planting resumed on 14.07.2021 the same interrupted. Most of the people wanted rework in alignment. Report the matter to Distr