Valiyapalam Bridge at Puthiyapalam
In progress65%Physical progress
43.7%Financial progress
Scheduled start26-06-2023
Scheduled completion04-07-2025
- Contractor
- PMRConstruction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,50,94,216₹19.51 crore
- Amount paid
- ₹8,53,16,149₹8.53 crore
- Paid to contractor
- ₹7,98,93,495₹7.99 crore
- Administrative sanction (AS)
- ₹60,00,00,000₹60 crore
- Financial sanction (FS)
- ₹59,01,00,000₹59.01 crore
- Technical sanction (TS)
- ₹18,16,58,166₹18.17 crore
- Tender amount
- ₹19,50,94,216₹19.51 crore
- Current progress
- Work tendered on 5/4/2022. Being single bidder qualified, work re-tendered on 23.04.2022 . Financial bid approved on Tender Approval Committee dated 22/6/2022. Requires subproject revision. Few land (5nos) required to acquire through Act are under prog