Cherttiyarazhikath bridge
In progress100%Physical progress
86.6%Financial progress
Scheduled start22-07-2019
Scheduled completion31-12-2025
- Contractor
- M/s K. T. Mathew&co
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹11,29,54,476₹11.3 crore
- Amount paid
- ₹10,54,21,913₹10.54 crore
- Paid to contractor
- ₹9,75,63,435₹9.76 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹12,20,22,668₹12.2 crore
- Technical sanction (TS)
- ₹12,31,99,879₹12.32 crore
- Tender amount
- ₹11,22,44,524₹11.22 crore
- Letter of acceptance (LOA)
- ₹11,22,44,524₹11.22 crore
- Current progress
- All 22 piles out of 22 completed. Both abutments and 7 girder beam completed. Drainwork completed retaining wall nearing completion in Kulakkada side. Drain work and retaining wall started in Mannadi side. Culvert at Kulakkada side completed for a length