Total of works

₹12.2 crore

₹12,20,22,668

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Cherttiyarazhikath bridge

Scheduled completion was 31-12-2025. That was 275 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Cherttiyarazhikath bridge

In progress
100%Physical progress
86.6%Financial progress
Scheduled start22-07-2019
Scheduled completion31-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹11,29,54,476₹11.3 crore
Amount paid
₹10,54,21,913₹10.54 crore
Paid to contractor
₹9,75,63,435₹9.76 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹12,20,22,668₹12.2 crore
Technical sanction (TS)
₹12,31,99,879₹12.32 crore
Tender amount
₹11,22,44,524₹11.22 crore
Letter of acceptance (LOA)
₹11,22,44,524₹11.22 crore
Current progress
All 22 piles out of 22 completed. Both abutments and 7 girder beam completed. Drainwork completed retaining wall nearing completion in Kulakkada side. Drain work and retaining wall started in Mannadi side. Culvert at Kulakkada side completed for a length

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹12,20,22,668₹12.2 crore

Details

Project code
PWD016-07-01
Department
Public Works
Constituency
Kottarakkara

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026