Mayyanad ROB
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹50,00,00,000₹50 crore
- Financial sanction (FS)
- ₹48,33,35,756₹48.33 crore
- Current progress
- LA requisition submitted to District Collector on 24.12.2018 and 4(1) notification was published on 18.06.2020. SIA study was completed 11(1) notification was published on 02.11.2021. BVR approved by District Collector on 25.02.2022. Survey completed. RR