Kallumthazham Junction ROB
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹50,00,00,000₹50 crore
- Financial sanction (FS)
- ₹30,93,40,653₹30.93 crore
- Current progress
- LA requisition submitted 04.10.2019. AS for LA GO(Rt) No 3108/2019/RD dt.30.10.2019. Stone planting put on hold. LA can be taken up only after the approval of GAD by Railway Authority. GAD was 1st submitted to Railways on 11.02.2019. After several revis