Kanakkuമലയാളം

Total of works

₹30.93 crore

₹30,93,40,653

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Kallumthazham Junction ROB

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹50,00,00,000₹50 crore
Financial sanction (FS)
₹30,93,40,653₹30.93 crore
Current progress
LA requisition submitted 04.10.2019. AS for LA GO(Rt) No 3108/2019/RD dt.30.10.2019. Stone planting put on hold. LA can be taken up only after the approval of GAD by Railway Authority. GAD was 1st submitted to Railways on 11.02.2019. After several revis

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹30,93,40,653₹30.93 crore

Details

Project code
PWD016-15
Department
Public Works
Constituency
Eravipuram

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kallumthazham Junction ROB
  • Scheduled start and completion dates · Kallumthazham Junction ROB
  • Amount paid · Kallumthazham Junction ROB

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…