Nayarthodu Bridge
In progress91.2%Physical progress
78.9%Financial progress
Scheduled start06-10-2022
Scheduled completion04-08-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹55,33,94,427₹55.34 crore
- Amount paid
- ₹43,66,14,748₹43.66 crore
- Paid to contractor
- ₹40,88,63,744₹40.89 crore
- Administrative sanction (AS)
- ₹48,00,00,000₹48 crore
- Financial sanction (FS)
- ₹56,85,76,616₹56.86 crore
- Technical sanction (TS)
- ₹50,55,40,279₹50.55 crore
- Tender amount
- ₹52,52,55,629₹52.53 crore
- Current progress
- Tender work in progress. Fixing of alignment stonework arranged.6(1) notification published on 19.052022