Kizhakkethala Chethupalam Flyover
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Financial sanction (FS)
- ₹89,92,14,928₹89.92 crore
- Current progress
- NOC from NHAI was obtained on 12.10.2021. LA requisition submitted to DC, Malappuram on 28.10.2021. Joint site inspection was conducted with Hon. MLA & Municipal Chairman on 01.12.2021. In this meeting, they requested to change the starting point in th