Total of works

₹36.51 crore

₹36,50,59,310

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Anjudi - Kundungal Bridge

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹17,00,00,000₹17 crore
Financial sanction (FS)
₹36,50,59,310₹36.51 crore
Current progress
FS obtained. Revenue order for LA obtained. LA requisition submitted to govt. Work for fixing the alignment stone is arranged 6(1) notification published on Gazette 17/03/2022

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹36,50,59,310₹36.51 crore

Details

Project code
PWD016-34
Department
Public Works
Constituency
Tanur

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Anjudi - Kundungal Bridge
  • Scheduled start and completion dates · Anjudi - Kundungal Bridge
  • Amount paid · Anjudi - Kundungal Bridge