PWD016-38-01 Kalliasseri

2017-18 Construction of New Bridge at Pazhayangadi in Kannur District- Contract work

Estimated amount

₹22.52 crore

₹22,51,50,000 · ₹10.95 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Pazhayangadi Bridge

Scheduled completion was 01-09-2025. That was 396 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Pazhayangadi Bridge

In progress
60%Physical progress
50.1%Financial progress
Scheduled start02-09-2023
Scheduled completion01-09-2025
Contractor
TAAbdul Rahiman
Implementing agency (SPV)
KRFB
Contract amount
₹21,21,17,914₹21.21 crore
Amount paid
₹10,63,73,665₹10.64 crore
Paid to contractor
₹10,05,14,092₹10.05 crore
Administrative sanction (AS)
₹35,00,00,000₹35 crore
Financial sanction (FS)
₹22,51,50,000₹22.52 crore
Technical sanction (TS)
₹19,47,59,173₹19.48 crore
Tender amount
₹21,21,17,914₹21.21 crore
Current progress
TS accorded and Bid Document Preparation is under progress from PD office.

Money trail

Estimated amount
₹22,51,50,000₹22.52 crore
Expenditure reported
₹10,94,78,44448.6% of the estimated amount

Details

Project code
PWD016-38-01
Department
Public Works
Constituency
KalliasseriMLA: Shri M. Vijin
Name as KIIFB publishes it
KIIFB 2017-18 Construction of New Bridge at Pazhayangadi in Kannur District- Contract work

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…