Kanakkuമലയാളം

Total of works

₹2.41 crore

₹2,41,11,244

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Moolakkeelkadavu

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹2,41,11,244₹2.41 crore
Current progress
Additional investigation work completed.Report to be obtained.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹2,41,11,244₹2.41 crore

Details

Project code
PWD016-40
Department
Public Works
Constituency
Payyanur

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Moolakkeelkadavu
  • Scheduled start and completion dates · Moolakkeelkadavu
  • Amount paid · Moolakkeelkadavu

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…