Sivagiri Thoduve Palam
Approved1%Physical progress
Not publishedFinancial progress
Scheduled start14-09-2024
Scheduled completion13-09-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹12,22,76,940₹12.23 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹40,00,00,000₹40 crore
- Financial sanction (FS)
- ₹10,47,76,294₹10.48 crore
- Technical sanction (TS)
- ₹9,84,34,264₹9.84 crore
- Tender amount
- ₹12,22,76,940₹12.23 crore
- Current progress
- TS estimate will be submitted after receiving KSEB utility shifting estimate. Puramboke assessment completed.