Anakkampoil Kalladi Meppadi Tunnel Road
Approved0%Physical progress
5%Financial progress
Scheduled start16-09-2025
Scheduled completion15-09-2029
- Contractor
- Not published
- Implementing agency (SPV)
- KRCL
- Contract amount
- ₹13,41,00,00,000₹1,341 crore
- Amount paid
- ₹67,05,00,000₹67.05 crore
- Paid to contractor
- ₹64,77,71,186₹64.78 crore
- Administrative sanction (AS)
- ₹6,58,00,00,000₹658 crore
- Financial sanction (FS)
- ₹21,34,50,00,000₹2,134.5 crore
- Technical sanction (TS)
- ₹16,43,32,27,730₹1,643.32 crore
- Tender amount
- ₹13,41,00,00,000₹1,341 crore