Kannur Airport Connectivity Roads

Total of works

₹964.72 crore

₹9,64,72,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Mananthavady - Boys Town - Peravoor - Sivapuram - Mattannur road

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Financial sanction (FS)
₹9,64,72,00,000₹964.72 crore

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹9,64,72,00,000₹964.72 crore

Details

Project code
PWD020-02
Department
Public Works
Constituency
Mattannur, Peravoor

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Mananthavady - Boys Town - Peravoor - Sivapuram - Mattannur road
  • Scheduled start and completion dates · Mananthavady - Boys Town - Peravoor - Sivapuram - Mattannur road
  • Amount paid · Mananthavady - Boys Town - Peravoor - Sivapuram - Mattannur road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256