Construction of MRS at Aralam in Kannur District -Solar System
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Technical Sanction Created · How we group
Money trail
- Estimated amount
- ₹18,60,00,000Estimate of sub-project SCD003-04, shared by 5 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 5 packages
- ₹17,30,81,77893.1% of the estimated amount
Details
- Project code
- SCD003-04-05
- Department
- Scheduled Tribe Development
- Executing agency
- Kerala State Construction Corporation Ltd.
- Constituency
- PeravoorMLA: Shri Sunny Joseph
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Construction of Model Residential School at Aralam, Kannur”. The figures below are for that whole project, not this package alone.
- Approved
- ₹18,60,00,000₹18.6 crore
- Paid so far
- ₹18,03,04,21896.9% of the amount approved
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- STDD - Construction of Model Residential School, Hostels, canteen and Staff Quarters at Aralam in Kannur District - Civil works ₹16.18 crore spent
- Electrification of Model Residential School at Aralam in Kannur District ₹75.03 lakh spent
- Fire Fighting System for MRS at Aralam in Kannur District ₹37.31 lakh spent
- Solar System for Model Residential School at Aralam in Kannur District Not published