Mundayad-Civil & Electrical
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Design Basis Report Created · How we group
Money trail
- Estimated amount
- ₹44,97,75,335Estimate of sub-project SYA001-07, shared by 2 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 2 packages
- Not published
Details
- Project code
- SYA001-07-01
- Department
- Sports & Youth Affairs
- Executing agency
- Sports Kerala Foundation
- Constituency
- KannurMLA: Shri Ramachandran Kadannappalli
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Jimmy George Indoor Stadium and Sports Complex at Kannur Mundayad”. The figures below are for that whole project, not this package alone.
- Approved
- ₹44,97,75,335₹44.98 crore
- Paid so far
- ₹00% of the amount approved
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…