Kanakkuമലയാളം

Estimated amount

₹38.59 crore

₹38,58,50,643 · ₹6.75 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹38,58,50,643₹38.59 crore
Expenditure reported
₹6,75,32,32217.5% of the estimated amount

Details

Project code
SYA001-08-01
Department
Sports & Youth Affairs
Executing agency
KITCO Ltd
Constituency
VarkalaMLA: Shri V. Joy

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Thomas Sebastian Indoor Stadium, Thiruvananthapuram”.

Approved
₹38,58,50,643₹38.59 crore
Paid so far
₹7,26,07,65418.8% of the amount approved

This package

Work awarded
₹7.26 crorepaid
₹7.26 croreapproved

Source: KIIFB project status (kiifb.org). Checked 01-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…