SYA004-04-01 Tanur

Thanur - Civil &Electrical

Estimated amount

₹10.07 crore

₹10,07,00,000 · ₹7 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹10,07,00,000₹10.07 crore
Expenditure reported
₹6,99,90,99869.5% of the estimated amount

Details

Project code
SYA004-04-01
Department
Sports & Youth Affairs
Executing agency
KITCO Ltd
Constituency
TanurMLA: Shri V. Abdurahiman

What KIIFB approved and paid

On KIIFB's project status page this belongs to “THANOOR STADIUM”.

Approved
₹10,07,00,000₹10.07 crore
Paid so far
₹7,57,90,41275.3% of the amount approved

This package

Work started
₹7.53 crorepaid
₹8.57 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress