This package
Work started₹14.64 crorepaid
₹15.27 croreapproved
₹13.33 crore
₹13,32,97,491
KIIFB status: Contract Process Completed · How we group
On KIIFB's project status page this belongs to “Improvements to WSS of Kondotty Municipality”. The figures below are for that whole project, not this package alone.
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: