WRD005-127-02 Kaipamangalam

Project 2 - CWSS to Nattika Firka – Replacing damaged 500mm Premo pipe by 500mm DI K9 pipe from CV Centre to Agastheswaram temple – Reach I

Spent on this package so far

₹3.81 crore

₹3,81,47,354

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹52,78,92,000Estimate of sub-project WRD005-127, shared by 7 contract packages
Expenditure reported · this package
₹3,81,47,354
Expenditure reported · all 7 packages
₹17,39,72,59333% of the estimated amount

Details

Project code
WRD005-127-02
Department
Water Resources
Constituency
KaipamangalamMLA: Shri E. T. Taison Master

What KIIFB approved and paid

On KIIFB's project status page this belongs to “WRD005-Trissur Ph Circle”. The figures below are for that whole project, not this package alone.

Approved
₹52,78,92,000₹52.79 crore
Paid so far
₹21,94,69,72641.6% of the amount approved

This package

Work awarded
₹3.95 crorepaid
₹9.44 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project