This package
Work awarded₹16.85 crorepaid
₹35.27 croreapproved
₹12.54 crore
₹12,53,71,313
KIIFB status: WBS Base One Approved · How we group
On KIIFB's project status page this belongs to “Laying distribution lines of Water Supply Schemes under KIIFB funding- WSS to Koyilandy Municipality Phase II”. The figures below are for that whole project, not this package alone.
Source: KIIFB project status (kiifb.org). Checked 04-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: