WRD022-01-02 Taliparamba

Construction of Regulator cum Bridge

Total of works

₹26.07 crore

₹26,06,77,922

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · #1

Scheduled completion was 15-01-2026. That was 260 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Work 1

In progress
25%Physical progress
21.8%Financial progress
Scheduled start16-10-2023
Scheduled completion15-01-2026
Implementing agency (SPV)
KIIDC
Contract amount
₹33,19,53,088₹33.2 crore
Amount paid
₹7,23,51,872₹7.24 crore
Paid to contractor
₹6,77,53,234₹6.78 crore
Administrative sanction (AS)
₹31,50,00,000₹31.5 crore
Financial sanction (FS)
₹26,06,77,922₹26.07 crore
Technical sanction (TS)
₹25,99,99,805₹26 crore
Tender amount
₹33,19,53,088₹33.2 crore
Current progress
Work gets halted for the last one year because of the case filed by the contractor to the honorable high court.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹26,06,77,922₹26.07 crore

Details

Project code
WRD022-01-02
Department
Water Resource
Constituency
Taliparamba

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…