Work 1
In progress25%Physical progress
21.8%Financial progress
Scheduled start16-10-2023
Scheduled completion15-01-2026
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹33,19,53,088₹33.2 crore
- Amount paid
- ₹7,23,51,872₹7.24 crore
- Paid to contractor
- ₹6,77,53,234₹6.78 crore
- Administrative sanction (AS)
- ₹31,50,00,000₹31.5 crore
- Financial sanction (FS)
- ₹26,06,77,922₹26.07 crore
- Technical sanction (TS)
- ₹25,99,99,805₹26 crore
- Tender amount
- ₹33,19,53,088₹33.2 crore
- Current progress
- Work gets halted for the last one year because of the case filed by the contractor to the honorable high court.