WRD022-02-01 Mankada

Construction of Regulator cum Bridge

Total of works

₹67.64 crore

₹67,64,35,620

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · RCB at Kezhmurikkadavu

Scheduled completion was 31-03-2026. That was 185 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

RCB at Kezhmurikkadavu

In progress
92.4%Physical progress
62.8%Financial progress
Scheduled start26-09-2020
Scheduled completion31-03-2026
Implementing agency (SPV)
KIIDC
Contract amount
₹64,19,74,680₹64.2 crore
Amount paid
₹40,29,89,183₹40.3 crore
Paid to contractor
₹37,67,65,192₹37.68 crore
Administrative sanction (AS)
₹70,00,00,000₹70 crore
Financial sanction (FS)
₹67,64,35,620₹67.64 crore
Technical sanction (TS)
₹66,94,00,000₹66.94 crore
Tender amount
₹57,56,06,461₹57.56 crore
Letter of acceptance (LOA)
₹57,56,06,461₹57.56 crore
Current progress
64out of 64 piles completed girder beam 28/48 concreted and erected. Open footing 6 out of 6 completed Deck slab between Abutment 2 to Pier 6 completed side protection 1)D/S-R/S- 230/260 M raft & Wall completed. 2)U/S-R/S- 486 m/600 m raft completed. 456

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹67,64,35,620₹67.64 crore

Details

Project code
WRD022-02-01
Department
Water Resources
Constituency
Mankada

What we don't know yet