RCB at Kezhmurikkadavu
In progress92.4%Physical progress
62.8%Financial progress
Scheduled start26-09-2020
Scheduled completion31-03-2026
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹64,19,74,680₹64.2 crore
- Amount paid
- ₹40,29,89,183₹40.3 crore
- Paid to contractor
- ₹37,67,65,192₹37.68 crore
- Administrative sanction (AS)
- ₹70,00,00,000₹70 crore
- Financial sanction (FS)
- ₹67,64,35,620₹67.64 crore
- Technical sanction (TS)
- ₹66,94,00,000₹66.94 crore
- Tender amount
- ₹57,56,06,461₹57.56 crore
- Letter of acceptance (LOA)
- ₹57,56,06,461₹57.56 crore
- Current progress
- 64out of 64 piles completed girder beam 28/48 concreted and erected. Open footing 6 out of 6 completed Deck slab between Abutment 2 to Pier 6 completed side protection 1)D/S-R/S- 230/260 M raft & Wall completed. 2)U/S-R/S- 486 m/600 m raft completed. 456