WRD022-04-01 Perambra

Construction of Regulator cum Bridge

Total of works

₹72.63 crore

₹72,63,27,930

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · RCB at Perincheri Kadavu

Scheduled completion was 31-03-2026. That was 185 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

RCB at Perincheri Kadavu

In progress
24.8%Physical progress
27.6%Financial progress
Scheduled start17-09-2020
Scheduled completion31-03-2026
Implementing agency (SPV)
KIIDC
Contract amount
₹68,46,94,229₹68.47 crore
Amount paid
₹18,88,78,068₹18.89 crore
Paid to contractor
₹17,66,57,513₹17.67 crore
Administrative sanction (AS)
₹57,00,00,000₹57 crore
Financial sanction (FS)
₹72,63,27,930₹72.63 crore
Technical sanction (TS)
₹63,90,00,000₹63.9 crore
Tender amount
₹68,46,94,229₹68.47 crore
Letter of acceptance (LOA)
₹61,13,34,133₹61.13 crore
Current progress
leftside retaining wall u/s 25/25m & d/s 25/50m completed. .Trestle pier P1 first lift completed . Abutment 3rd lift concrete completed Current Financial Progress : 17% Achieved progress

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹72,63,27,930₹72.63 crore

Details

Project code
WRD022-04-01
Department
Water Resources
Constituency
Perambra

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…