RCB at Perincheri Kadavu
In progress24.8%Physical progress
27.6%Financial progress
Scheduled start17-09-2020
Scheduled completion31-03-2026
- Contractor
- T. B. Abdul Salam
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹68,46,94,229₹68.47 crore
- Amount paid
- ₹18,88,78,068₹18.89 crore
- Paid to contractor
- ₹17,66,57,513₹17.67 crore
- Administrative sanction (AS)
- ₹57,00,00,000₹57 crore
- Financial sanction (FS)
- ₹72,63,27,930₹72.63 crore
- Technical sanction (TS)
- ₹63,90,00,000₹63.9 crore
- Tender amount
- ₹68,46,94,229₹68.47 crore
- Letter of acceptance (LOA)
- ₹61,13,34,133₹61.13 crore
- Current progress
- leftside retaining wall u/s 25/25m & d/s 25/50m completed. .Trestle pier P1 first lift completed . Abutment 3rd lift concrete completed Current Financial Progress : 17% Achieved progress